Glasa Wind Farm

Coriolis Energy and ESB are bringing forward plans to develop a wind farm, located in Ross-shire, on an area of moorland within the Strathvaich and Kildermorie Estates, approximately 20km northwest of Dingwall.

The second consultation period for Glasa Wind Farm is now underway. You can view the information shared as part of this consultation below, or if you prefer you can download the materials here.

Summary

We are proposing a wind farm of up to 28 turbines with a maximum blade tip height of 250m, capable of generating approximately 196MW of renewable energy. The site is located around 20km north-west of Dingwall in the Highlands and lies within an area identified by The Highland Council as having potential for wind energy development.

The location benefits from good access to the local road network and proximity to the electricity transmission network. If consented, Glasa Wind Farm could generate enough renewable electricity to power approximately 111,000 homes and would provide a community benefit fund of up to £5,000 per MW of installed capacity. Opportunities for community ownership are also being explored.

The proposed development includes associated infrastructure such as access tracks, underground cabling, construction compounds and battery energy storage equipment. The project will also seek to deliver biodiversity enhancements through habitat restoration and management measures, helping to protect and improve the local environment.

Site location indicated by the red outline

Our updated proposals include:

Since the early proposal was shared during our April 2025 consultation, we have made a number of key changes to our proposals based on your feedback, further surveys, stakeholder consultation and site assessments

Key design changes include:

  • Reducing landscape and visual effects – Turbines have been repositioned to create a more coherent layout within the Site’s natural landscape, while balancing wind-energy performance, environmental constraints and buildability.
  • Reducing impacts on peatland, lochans and watercourses – Infrastructure has been moved or removed where practicable to reduce effects on deeper peat. In particular, the access-track network has been redesigned in several locations to shorten routes, reduce watercourse crossings and make greater use of existing tracks and areas of shallower peat.
  • Reducing impacts on biodiversity – Ecological and ornithological survey findings have informed the layout, with turbines, tracks and other infrastructure positioned to avoid or minimise effects on sensitive habitats, protected species and key bird areas where practicable.

Glasa Wind Farm could:

Generate up to 196MW

of renewable energy, equivalent to the annual needs of up to 181,972 homes per year.

Provide a Community Benefit Fund

of up to £5k per MW, for the lifetime of the project (up to 40 years).

Deliver a net biodiversity benefit

through an agreed Habitat Management Plan, which ensures the development will leave biodiversity and ecosystems in a better state than before.  

Offer community ownership

giving local people the opportunity to own a share in the wind farm.

Provide job opportunities

and support the local supply chain during construction and operation. 

Generate local business opportunities

We welcome local businesses and suppliers to connect with us and join our dedicated ‘Local Supplier Register’. This allows businesses interested in the project to share their details and explore opportunities to get involved. Feel free to reach out and register your interest. We are committed to collaborating with local businesses and will be hosting a Meet the Developer events to discuss potential opportunities

As part of the development process, we will conduct an Environmental Impact Assessment (EIA) to evaluate the potential impact of the proposed Glasa Wind Farm on the surrounding natural environment.

The Applicant has appointed RSK Environment Ltd (RSK), an experienced environmental consultancy based in Glasgow, as lead consultant to carry out an EIA and related assessments to accompany a Section 36 Application1 to the Scottish Ministers.

The EIA process includes:

  • Consultation with the local authority, stakeholder organisations and the public to identify specific concerns and issues;
  • Determining the existing conditions at and around the site by reviewing the available data and undertaking specialist field surveys;
  • Assessing the potential impacts on the existing environment; and
  • Developing proposals for mitigation measures to alleviate any significant impacts identified.

The Applicant has conducted a detailed scoping exercise to identify the environmental aspects to address in the EIA.

The EIA will cover the following areas:

  • Landscape and Visual;
  • Ecology and Ornithology;
  • Geology, Hydrology, Hydrogeology and Peat;
  • Noise and Vibration;
  • Traffic and Movement;
  • Climate Change and Carbon Balance; and
  • Forestry.

Due to the remote location of the site, the following topics have been scoped out of the EIA: Air Quality, Population and Human Health, and Shadow Flicker. Assessment of Telecommunications, Aviation and Radar, and Archaeology and Cultural Heritage have also been scoped out of the EIA following consultation.

To date, the following surveys/activities have been undertaken:

  • Ornithology and Ecology surveys (inc. discussion with NatureScot to agree assessment scope and methodology);
  • Phase 1 and Phase 2 peat probing and peatland condition assessments (inc. discussions with SEPA to inform approach to minimising peat disturbance and avoiding deep peat where practicable);
  • Landscape and visual field work and photography from viewpoint locations agreed with The Highland Council;
  • Planning policy appraisal;
  • Assessment of site-specific constraints;
  • Archaeology walkover and consultation with Historic Environment Scotland; and
  • Hydrology walkover.

An EIA Report will be submitted as part of our application.

The following supporting documents will be submitted alongside the EIA Report as part of the S36 submission:

  • Socio-economics Statement;
  • Design and Access Statement;
  • Planning Statement;
  • Pre-Application Consultation Report; and
  • Heritage Impact Assessment.
Proposed turbine locations and site layout

  1. All of these will form part of the formal application for consent made to the Scottish Ministers. This will summarise the data we have gathered, how our design has evolved to reflect this and any ways in which any remaining impacts could best be managed ↩︎

A Landscape and Visual Impact Assessment (LVIA) will be conducted to evaluate the potential effects of the wind farm on surrounding views and the landscape character of the area. The LVIA will also consider the implications of the proposed wind farm for designated landscapes and Wild Land Areas.

The following will be assessed:

  • Landscape character types, including key characteristics and valued elements;
  • The key attributes and qualities of Wild Land Area 29: Rhiddoroch – Beinn Dearg – Ben Wyvis;
  • The special qualities of Special Landscape Area 17: Ben Wyvis and Special Landscape Area 18: Fannichs, Beinn Dearg and Glencalvie; and
  • Views and visual amenity experienced by local residents, tourists/ visitors, recreational and transport users in the area.

The Zone of Theoretical Visibility (ZTV) map below shows where the turbine blade tips may be visible. It also shows the 20 viewpoints that will be used for the Landscape and Visual Impact Assessment (LVIA). The project team selected these viewpoints following site visits, and they have been agreed with The Highland Council.

Illustrations (photomontages) from the following viewpoint locations are shown below:

  • The summit of Ben Wyvis;
  • The A835 at Black Bridge;
  • The summit of Carn Chuinneag; and
  • The summit of Am Faochagach.

Each viewpoint has been illustrated with a photomontage showing the proposed development.

VP2: Carn Chuinneag

VP4: A835, west of Black Bridge

VP5: Am Faochagach

VP7: Ben Wyvis – Glas Leathad Mor


A Zone of Theoretical Visibility (ZTV) map is a computer-generated tool that establishes the theoretical extent of the visibility of the proposed turbines across the 45km LVIA Study Area. The ZTV has been calculated to blade tip height. This has helped with the identification of representative viewpoints and informed the scope of the LVIA. The ZTV does not take account of buildings and vegetation, which can reduce actual visibility in the field where there is notable tree cover or settlements.

Zone of Theoretical Visibility map

A cumulative Landscape and Visual Impact Assessment will be undertaken in accordance with NatureScot guidance. The cumulative assessment will consider additional and combined effects with other proposed wind farm developments.

Other wind farm developments to be included in the Cumulative Assessment

A programme of ecological and ornithological surveys have been carried out on the site. The results have informed the design of the wind farm so that impacts on habitats and wildlife can be avoided where possible. The survey information will help assess and mitigate any residual impacts on natural heritage and identify opportunities to provide habitat and species enhancements as part of the development

The following ornithology surveys form the baseline for the assessment and were conducted within the proposed design layout:

  • Flight activity surveys (monthly from March 2024 to August 2025);
  • Scarce breeding bird surveys (2024 and 2025 breeding seasons);
  • Black grouse surveys (2024 and 2025 breeding seasons);
  • Breeding wader surveys (2024 and 2025 breeding seasons); and
  • Winter walkover surveys (2024/2025 non-breeding season).

From the baseline surveys and consultation with the Highland Raptor Study Group, black grouse, golden eagle, black-throated diver, curlew, dunlin, golden plover and greenshank have been identified to be the key target species present within the study area.

The ecology surveys undertaken include:

  • A Phase 1 habitat survey;
  • National Vegetation Classification (NVC) surveys;
  • Protected species surveys;
  • Fish habitat and electrofishing surveys; and
  • Peatland condition survey.

The site mainly consists of damaged peat bog and wet moorland. In some places, the peat has been worn away, creating channels, exposed banksand areas of bare peat. Smaller areas of grassland, drier heath and other wetland habitats are also present. Much of the site contains peatland that is important for wildlife and for storing carbon.

The potentially important protected species recorded during baseline surveys of the site include otter, water vole, mountain hare, common lizard and bats.


Peat areas shown in relation to the proposed site layout

Potential impacts on groundwater quality or quantity, flood risk, water quality and private water supplies, and changes to peat and carbon-rich soils will be considered in the EIA.

Extensive peat-depth surveys have been conducted, which found variable areas of peat onsite. Areas of deep peat have been avoided where possible in the design of the proposed Glasa Wind Farm.

Existing tracks have been used as much as possible to minimise new track construction. This will minimise the impact on peat and carbon-rich soils and the requirement for new watercourse crossing structures.

Surveys on site have identified extensive areas of degraded peat. This presents a great opportunity for peatland restoration to be included as part of further biodiversity enhancements across the site. Details of any enhancements will be included within a Biodiversity Enhancement Management Plan (BEMP) submitted as part of the application for consent.

The site has very low flood risk, with only small pockets of high flood risk associated with rainfall to the north of the site at Loch na Glasa and around the existing watercourses on the site and the design has evolved to reduce impacts on these areas.

There are several private water supplies within 5 km of the site, along with two surface water drinking protected areas nearby, which could potentially be affected by the proposed development. These areas include:

  • Loch Glass, located downstream from the Abhainn Beinn nan Eun; and
  • Loch Morie, located downstream from the Abhainn na Glasa.

The proposed Glasa Wind Farm turbines and associated infrastructures will be carefully designed to minimise the risk of pollution to watercourses, and these issues will be fully addressed as part of the EIA.


The proposed abnormal indivisible load delivery route

An abnormal indivisible load route review (ALRR) has been undertaken for the proposed turbine locations to identify the appropriate work required to accommodate the delivery of abnormal load from the port of entry to the Site.

A preliminary ALRR has been undertaken to assess transport routes for Wind Turbine Generator components from port of entry to site. The preferred access route for the project involves using the Port of Nigg as the main port of entry for all components. Road access will be via the B9175, the A9(T), and the A835(T) from Tore Roundabout towards Ullapool.

An appropriate access junction will be provided to cater for general construction traffic, abnormal loads deliveries and it is anticipated that this will be a modified layout of the existing access from the A835(T) to the east of the Black Bridge.

Potential traffic-related environmental effects, such as delays, impacts on pedestrian journeys, and accidents and safety, will be considered in the EIA and assessed for the construction period where traffic generation will be greatest. Cumulative traffic and transport effects will also be assessed where the construction of Glasa Wind Farm could overlap with other known projects using the same road network. A Construction Traffic Management Plan will be developed in consultation with the Council, to help reduce disruption caused by traffic on local roads.


The Environmental Impact Assessment process also considers several other factors through which Glasa Wind Farm could impact the environment.

Initial modelling of noise levels has been undertaken as part of the site
evaluation process. As the nearest residences are located approximately
4 km from the proposed turbines the predicted noise levels are very low.
However, an operational noise assessment will still form part of the EIA.
Likewise, construction noise may require assessment for access-track
works and traffic near receptors

There are areas of woodland within the site, with blocks of ancient and native woodland within the southern portion of the site. No wind turbines will be proposed within woodland areas. However, there is an area mapped as ancient woodland north of Strathvaich Lodge through which an existing track runs that will be widened as part of the proposed development. If any potential direct impacts on woodland from site access cannot be avoided by design, compensatory planting will be provided. The project team will also explore whether there are opportunities for woodland planting to form an integral part of the project’s biodiversity enhancement commitments.


The EIA focuses on identifying and assessing likely significant environmental effects and the measures needed to avoid or reduce them. The following topics have been scoped out of the EIA because significant effects are unlikely. However, they have not been disregarded and will still be addressed where relevant through supporting application documents, design measures and management plans.

A Heritage Impact Assessment (HIA) will be submitted with the application for consent. The proposed Glasa Wind Farm turbines and associated infrastructure have been designed to avoid known archaeological or cultural heritage assets of importance within the site. In the wider area, the proposed turbines will be intervisible with very few heritage assets. Ardross Castle and a number of scheduled monuments to the east of the site which do lie within the ZTV were considered at scoping stage; no significant adverse effects are anticipated upon their settings.

An assessment of the potential socio-economic effects of the Glasa Wind Farm on tourism, recreation, land use, economic output, employment generation and other indirect effects will be undertaken and included with the application for consent.

In addition, the Socio-economic Statement will be prepared in line with the emerging Scottish Renewables NPF4 Policy 11(c) reporting framework and Scottish Government policy objectives. It will outline how the applicant intends to maximise net economic impact and deliver benefits at the local, regional and national levels.

A preliminary review has confirmed that the proposed wind farm will not have a significant impact on civil or military radar systems.

While the site is located within two low-flying military zones and an assessment area for Inverness Airport, no significant effects on aviation have been identified. Therefore, further assessment of aviation factors have been scoped out of the EIA.

Following community feedback from the first consultation, it is possible that visible aviation lighting will not form part of Glasa Wind Farm subject to agreement with the Civil Aviation Authority (CAA) and other aviation stakeholders.

Review of the Ofcom Spectrum Information Portal and Wireless Telegraphy Register has determined that there are no fixed telecommunications links within 5 km of where turbines are proposed. In view of the remoteness of the site and the absence of residential properties in the area it is considered to be extremely unlikely that the proposal could have any impacts on terrestrial television reception.

Shadow Flicker is an effect caused in particular circumstances by the rotation of the turbine blades when the sun is shining, which can create a flickering or strobe-like effect. This can be a cause of annoyance at residences near wind farm developments. However, the proposed Glasa Wind Farm is too far from potential shadow flicker receptors (>4 km from nearest property) and therefore there are no shadow flicker impacts predicted.


Coriolis Energy and ESB will work closely with local communities, businesses and residents in seeking to ensure that they bring real benefits and help meet national climate change targets through Glasa Wind Farm.

We would like to hear from businesses across the Highlands to ensure that we can fully consider the skills and services of local people and suppliers if Glasa Wind Farm receives approval and proceeds to construction.

The opportunities available include those for:

  • An engineering, procurement and construction (EPC) contractor.
  • Construction material suppliers: concrete, aggregate and building materials.
  • Electrical contractors: supply and installation of plant, cabling, earthing, etc.
  • Plant and equipment hire contractors; excavation earthworks, cranage, welfare units, etc.
  • Labour hire companies: engineers, plant operatives and general labourers.
  • Transport: taxis and minibuses for local labourers.

If you are a local company and would like to register your interest in this proposal, please email: info@glasawindfarm.com.

Construction projects of this nature inevitably require some specialist technicians from outside the area, so they will require local accommodation and catering facilities. We would welcome expressions of interest from providers of accommodation and related services.

The Glasa Wind Farm project will establish a substantial community benefit fund, bringing direct investment to the local economy and creating job opportunities. Coriolis Energy and ESB are dedicated to sourcing as many components, materials, services, and supplies as possible from within the local and neighbouring authorities, ensuring that economic benefits stay close to home.

Our goals include creating local apprenticeships and prioritising the hiring of local site operatives and staff, helping to build a skilled workforce that can grow with the project.

We want to work in partnership with the local community to design a project which could bring a variety of direct benefits to the community.

We are committed to the Proposed Development being a shared ownership project if there is interest in the local community. Coriolis Energy invites the local community to discuss with us the opportunity for community investment in Glasa Wind Farm. Community investment would not affect the Community Benefit Fund.

We are committed to a £5,000 per MW fund for the Glasa Wind Farm proposals, which would mean up to £980,000 per annum for the local communities.

In developing detailed proposals for the community benefit fund, we will be guided by the Scottish Government’s Good Practice Principles for Community Benefit. Our approach begins with engaging local and neighbouring community councils, to gather their insights on defining the area of benefit and identifying local priorities. This collaborative foundation ensures the fund is designed to meet the unique needs of the community.


We received a range of feedback during our first round of consultation and are grateful those who took the time to share their views with us. Below shows how your feedback has informed the updated design.


Some feedback raised concerns about the visual impact of the proposals on the surrounding areas.


To reduce the visual impact of the development, we have drawn the turbines more tightly together. This has helped reduce the visual spread, create a layout that integrates more effectively with the site’s natural landscape, helping reduce visual impacts while continuing to balance wind energy performance and the practical delivery of the project.


Some respondents asked why the site was considered suitable for development, and cited a perceived oversaturation of local renewable projects


Our project is designed to support Scotland’s energy transition. Scotland has committed to achieving net zero carbon emissions by 2045, reducing reliance on fossil fuels and increasing renewable energy capacity, and this proposal would play a vital role in this. The site for Glasa Wind Farm was selected based on distance from residential properties, natural screening through the existing landscape, strong wind resource, and opportunities to deliver significant biodiversity enhancement.


Queries were received regarding the potential disruption of traffic during the construction of the development and how the impacts on the local road network would be managed, in particular travel along the A835 to the Ullapool ferries


We have undertaken detailed transport assessments to identify the most suitable route for turbine deliveries and construction traffic. The preferred route uses existing trunk and local roads and has been assessed to ensure it can safely accommodate abnormal loads.

Construction traffic will be managed through a Traffic Management Plan, which will be agreed with the council prior to construction starting. To minimise disruption, the programme for abnormal load deliveries will be shared with local communities and businesses , and these will be informed by the Ullapool ferry timetables. We will also liaise with emergency services throughout this period to keep them informed of turbine deliveryarrangements.


Feedback included concerns regarding the impacts on deep peat and regarding habitat restoration


Careful infrastructure design has been undertaken to avoid areas of deep peat and sensitive habitats wherever possible. More information about this is available as part of this consultation. Further surveys undertaken in 2025 and 2026 have identified the areas of most intact blanket bog and good quality habitats, and the access track network has been redesigned in several locations to avoid those areas, shorten routes and reduce watercourse crossings. This means that disturbance is more focused on areas of heavily degraded, shallow or bare peat areas within the site


Some respondents had concerns regarding the potential impacts on important bird species


Ecological and ornithological survey findings have informed the updates to the proposed layout, with turbines, tracks and other infrastructure positioned to avoid or minimise effects on sensitive habitats, protected species and key bird areas where practicable


Some feedback suggested that funding should reflect the scale of the project, and concerns were raised about whether the benefits would outweigh potential impacts on local roads, the environment and local communities


We will continue engaging with local communities throughout the development process to help shape community benefit proposals and ensure funding reflects local priorities. This includes a proposed £5,000 per MW community benefit fund, exploring opportunities for community ownership, supporting local employment and seeking to maximise the use of local suppliers to deliver meaningful benefits for the area.


Some feedback raised concerns regarding night-time visibility and aviation lighting effects


Following community feedback from the first consultation, it is possible that visible aviation lighting will not form part of Glasa Wind Farm subject to agreement with the Civil Aviation Authority (CAA) and other aviation stakeholders

Thank you for taking the time to find out more about our updated proposals for Glasa Wind Farm.

Please take a moment to tell us what you think about the proposals and have your say on our plans.